ISLAMABAD: A breakdown in the coal unloading conveyor at Pakistan International Bulk Terminal at Port Qasim has disrupted imported coal supplies, prompting Jamshoro Power Company to warn of potential pressure on fuel stocks and electricity generation.
According to the supplied report, the terminal’s sole coal unloading conveyor has been out of service since November 18. Daily unloading capacity has fallen from 30,000 tonnes to approximately 3,000 tonnes, a reduction of about 90 per cent. Cement and textile industries are also reported to be facing supply difficulties alongside power plants.
Jamshoro Power Company said coal was being unloaded manually at a much slower pace, prolonging the wait for coal vessels. It has written to the federal government and terminal management seeking urgent action, warning that a prolonged disruption could deplete stocks and affect power production.
The report states that the conveyor failed while coal was being unloaded from the vessel Pegasus 8 on November 18. Terminal management attributed the damage to excessive dust, sharp iron fragments and other foreign material in coal imported from Tanzania. Management estimated that repairs could take eight to ten days.
Five incoming vessels could face a combined $2 million to $3 million in additional demurrage charges, or costs associated with waiting, according to the report.
Jamshoro Power Company also warned of potential losses associated with approximately Rs2.2 billion in monthly capacity payments. These figures represent estimated exposure rather than confirmed losses.
Delays in coal deliveries could increase generation costs, prolong vessel congestion and disrupt industrial activity and electricity supply. The report places the disruption against existing pressure on the energy sector from interruptions in LNG supplies and reduced availability of hydropower.